Public Works

Paving for Progress Projects
2021 Project Highlights 

2nd Street SE, from 3rd Avenue to 4th Avenue

  • IMPROVEMENTS: Pavement improvements, water main, storm sewer, sanitary sewer, on-street bike lanes, and ADA sidewalk and ramp improvements
  • PROJECT TIMELINE: Summer 2021
  • TRAFFIC IMPACTS: Complete closure during construction

12th Avenue SE, from 7th Street to 17th Street

  • IMPROVEMENTS: Pavement improvements, water main, storm sewer, sanitary sewer, on-street bike lanes, and ADA sidewalk ramp improvements.
  • PROJECT TIMELINE: Spring 2021 - Fall 2022. 
  • TRAFFIC IMPACTS: Complete closures: Between 7th Street to 10th Street SE in 2021; between 11th Street SE to Americus Drive SE in 2022.

6th Street SW, from 33rd Avenue to Wilson Avenue

  • IMPROVEMENTS: New asphalt road surface, utilities, new traffic signals at 33rd Avenue and Wilson Avenue and a pedestrian signal at 29th Avenue, sidewalk on both sides of 6th Street SW. Private utility upgrades.
  • PROJECT TIMELINE: Majority of utility and road work 2021; sidewalk and remaining work 2022
  • TRAFFIC IMPACTS: Periodic full closures of side street intersections; two-way traffic maintained on 6th Street. Business access open.

32nd St NE Bridge, from Rosewood Court to Madison Street

  • IMPROVEMENTS: Pavement improvements and bridge deck rehabilitation, storm sewer, sanitary sewer, new traffic signals, new bridge rail, I-380 on/off ramp intersection improvements, and ADA sidewalk ramp improvements
  • PROJECT TIMELINE: April 2021 - September 2021
  • TRAFFIC IMPACTS: 32nd Street Bridge closed during construction. Alternating closures on each side of the bridge (the west side I-380 on-ramp area, and the east side on-ramp area). 

66th Avenue SW, from the CRANDIC Railroad to 8th Street

  • IMPROVEMENTS: Pavement improvements, , storm sewer, sanitary sewer, and sidewalk construction.
  • PROJECT TIMELINE: Spring 2021 - Fall 2022. 
  • TRAFFIC IMPACTS: Complete closure during construction in 2021 between CRANDIC Railroad to 8th Street. Access to businesses will be allowed within the project limits.

C Street SW, from Bowling Street to Handley Drive

  • IMPROVEMENTS: Pavement resurfacing, water main, storm sewer, ADA sidewalk ramp improvements and installation of new sidewalk.
  • PROJECT TIMELINE: 2021
  • TRAFFIC IMPACTS: Periodic full closures. Complete closure of Wilson Avenue Drive and C Street SW during construction of intersection.

Chandler Street SW and 20th Street SW Loop

  • IMPROVEMENTS: Pavement reconstruction, water main, sanitary sewer, and storm sewer reconstruction, sidewalk extension on 16th Avenue SW.
  • PROJECT TIMELINE: 
    2021: Utility work, pavement on 20th Street SW and sidewalk on 16th Avenue SW.
    2022: Complete remaining pavement construction on Chandler Street SW Loop.
  • TRAFFIC IMPACTS: All work at the Jefferson High School entrance off 20th Street SW will be under full closure during the summer. Single lane open at other locations.

Cottage Grove Avenue SE, from 1st Avenue to Forest Drive

  • IMPROVEMENTS: Complete reconstruction, water main replacement, storm sewer extension, sanitary sewer service improvements, off-street bike / pedestrian trail, traffic signal improvements, and sidewalk ADA improvements.
  • PROJECT TIMELINE: 2021. Work continues from Forest Drive to 34th Street in 2022. 
  • TRAFFIC IMPACTS: Full closure, local access only.

Council Street NE, from Collins Road to Blairs Ferry Road 

  • IMPROVEMENTS: Crack, seat and asphalt pavement overlay, minor water main , sanitary sewer service and sidewalk replacement. Driveway apron and intersection pavement replacement, new sidewalk and ADA sidewalk ramp improvements.
  • PROJECT TIMELINE: May 2021 - September 20221. 
  • TRAFFIC IMPACTS: One month closure of the intersection of Council Street and 51st Street/ Park Place Otherwise periodic lane closures between Collins Road to Blairs Ferry Road.

E Avenue NW, from West Post Road to Shetland Drive

  • IMPROVEMENTS: Asphalt resurfacing, drainage improvements and ADA sidewalk ramp upgrades
  • PROJECT TIMELINE: Spring 2021
  • TRAFFIC IMPACTS: Periodic full closures

Edgewood Road NW, from the Cedar River Bridge to Ellis Road 

  • IMPROVEMENTS: Pavement patching and asphalt pavement overlay
  • PROJECT TIMELINE: Summer 2021 - Fall 2021
  • TRAFFIC IMPACTS: Lane reductions in place

Oakland Road/Old Marion Road NE, from Center Street to Regent Street

  • IMPROVEMENTS: Pavement improvements, water main, storm sewer, sanitary sewer, on-street bike lanes, sidewalk infill and ADA sidewalk ramp improvements.
  • PROJECT TIMELINE: Spring 2021 - Fall 2022. 
  • TRAFFIC IMPACTS: Complete closure during construction in 2021 between Center Street and Miami Court. Complete closure during construction in 2022 between Miami Court and Regent Street. Access to businesses and residences will be allowed within the project limits.

O Avenue NW from Edgewood Road to 16th Street

  • IMPROVEMENTS: Complete roadway reconstruction, sidewalk, storm sewer, water main, sanitary sewer improvements, and installation of retaining walls in select areas. Private utility upgrades.
  • PROJECT TIMELINE:
    2020: Completed between 20th Street and 16th Street
    Winter 2020/2021: Utility work continues
    2021: 27th Street and 20th Street
    2022: 27th Street to Edgewood Road
  • TRAFFIC IMPACTS: Eastbound only between 27th Street and 20th Street. Two-way traffic between 30th Street and 27th Street. Temporary full closures throughout the project.
Full list of 2021 projects coming soon


Project Newsletters

 


Interactive Map
Click the map below for details on finished projects, or those underway:

Picture Link to Paving for Progress Project Map
 
© 2021  Cedar Rapids, Iowa, 101 First Street SE

Powered By Revize Login