35th Street NE, from Oakland Road to F Avenue

Pavement Reconstruction

SUBSCRIBE FOR PROJECT NEWSLETTERS

Project Phase: Construction
Construction Start: March 2024


Construction Update: June 14, 2024

35th Street is really starting to transform. The roadway paving is complete in Stage 1A, and the majority of the driveways are also complete. 

Upcoming Work (Next Two Weeks, Weather Permitting)

  • The contractor will continue to work on driveways and new sidewalks in this stage in the coming weeks. If the weather stays cool and dry, they may place sod. 
  • They will also continue installing the sanitary sewer east of Eastern Avenue, followed by paving in Stage 1B.

Traffic Impacts

  • 35th Street is closed to through traffic for the duration of the project.
  • Access will be maintained to residents within each stage for as long as possible during utility work.
  • Full closures at each stage are required for the roadway work.

Thank you for your patience.

Paving for Progress 35th St update June 14


Project Phasing

Map of project phases on 35th Street NE. There are six phases.

Description of Map Image:

  • Stage 1 is divided into three phases: A, B, and C.
    • Stage 1A begins about a half block west of Eastern Avenue NE and runs through just east of the Eastern Avenue NE intersection.
    • Stage 1B begins where Stage 1A ends, just east of the Eastern Avenue NE intersection, and ends just east of the Collins Aerospace parking lot.
    • Stage 1C begins where Stage 1B ends, just east of the Collins Aerospace parking lot, and ends just past the F Avenue NE intersection.
Construction Schedule:
  • Stage 1 work is scheduled for 2024.
  • Stage 1A work will begin on March 18, including the full closure of 35th Street NE and Eastern Avenue/Zach Johnson Drive intersection.
  • Stage 2 work is scheduled for 2025 and will also include three subphases.

The project is expected to be complete at the end of 2025, with some possible wrap-up work in Spring 2026.

Please note: 35th Street will be closed to through traffic for the project's duration. Access will be maintained to residents within each stage for as long as possible during utility work. Full closures at each stage will be required for the roadway work.

Past Updates


Key Contacts

Contractor
Rathje Construction
Dan Scofield
319-480-4970

City Construction Manager
Eric Bahl
319-286-5531 | e.bahl@cedar-rapids.org

City Project Manager
Jennifer Selby
319-286-5622 | j.selby@cedar-rapids.org


Planned Improvements

This project includes concrete pavement reconstruction, new sidewalk on both sides of the street, driveway replacements, new storm sewer installation, replacement of sanitary sewer from Eastern Avenue to approximately 808 35th Street, new street lighting, and pavement markings including a center line and on-street parking/“urban shoulder” lines.