Home > News List > Edgewood Road Bridge and Trail Improvements

Edgewood Road Bridge and Trail Improvements

Edgewood Road Bridge and Trail Improvements

February 29, 2024

Edgewood Road Trail Phase 2B is scheduled to begin March 4, 2024. This multi-phase project is located on the Edgewood Road bridge between Ellis Road NW and Glass Road NE. Construction will include bridge modifications to accommodate an eight-foot-wide trail with approximately 400 feet of additional trail extending north of the bridge; miscellaneous bridge repairs, additional; and water main replacement and relining, bringing the water main back online after being out of service since 2017.

Traffic control is planned to remain in place between March 4 and mid-September of this year with lane reductions to northbound and southbound traffic for all stages of work. Two-way traffic will be maintained throughout the duration of construction. Estimated timeline for each stage of work is as follows:

  • Stage 1: March 4, 2024 through late June 2024
  • Stage 2: Late June 2024 through late August 2024
  • Stage 3: Late August through mid-September 2024

Map of the staged work

 